Time Impact Analysis Defined
Compare the predicted completion of the schedule just prior to the date of the “delay event” to the predicted completion of the schedule after inserting a fragnet of impact activities into the schedule
Contemporaneous Prospective
Performed to “look-ahead” during project
Performed at moment of start of impact
Called Contemporaneous Time Impact Analysis (TIA)
What is Time Impact Analysis?
While Time Impact Analysis TIA focuses on the effect of the delays on the updated as planned program, by imposing the delays one by one on the updated as-planned schedule and compare it with the updated as-planned to see the event effect on the schedule,
with the delay included. It looks to calculate the duration variance between the two schedules to provide the contractor with a basis for estimating the delay impact.
then imposing the next and repeat the whole process again till we finalize imposing all delays,
Time Impact Analysis vs Impacted As Planned
• The Following Charts might show a small explanation for each method, and The Contractor shall assume and submit along with his claim report a detailed explanation for the method he adopted to present his E.O.T claim, with all the substantiation and support for his choice