Work at the Bagnell Dam is nearing completion! The dam received a structural upgrade of 16,000 cubic yards of mass concrete and 67 high capacity dam anchors. The most challenging phase of the project was working in the spillway, where Brayman was only given a 6 month window to install 33 anchors, INCLUDING erection and removal of a 520-ft long steel platform before the spring time rains.