Calculating float time on a non-critical path involves determining the amount of time that a task can be delayed without affecting the project's overall completion date. Float time, also known as slack, is the difference between the earliest and latest possible start times for a task. On non-critical paths, this allows for flexibility in scheduling, as these tasks don't directly influence the project's critical path or deadline.
#ProjectManagement #FloatTime #NonCriticalPath #SlackTime #SchedulingFlexibility