Fast and Furious Rapid Bridge Demo—Watch it all unfold in less than 8 hours.
The Priestly Demolition crew has to work smart to get the job done safely, and meet the deadline so that this busy road can re-open at 8 am Sunday morning.
Rapid demolition is nothing new for our crew, but this is a tighter timeline than usual, and the adrenaline is pumping!
On the job we've got 5-50T excavators, 1-70T, 3 loaders, hammers, grapples and processors. Crew did an an amazing job, and can't forget our on-site mechanics and fleet dept.
This is the 1st phase of demolition, with phase II scheduled for May 2024.
PDI is pleased to work with Brennan Paving & Construction on this project.