Maximize efficiency when operating a Ledwell Bulk Haul Feed Truck or Trailer by following the proper steps to load and unload.
To get started, walk around the entire trailer to inspect the following:
Overhead and ground obstructions
Hydraulic Valves in the neutral position
Hydraulic and Air Hoses
Lights
Wheels and Tires
Remote control
TO LOAD:
Pull up to the mill and position as needed.
Check that your bottom doors are closed.
Open the top doors
Fill the bins of the trailer.
TO UNLOAD:
Engage the PTO
Push raise and out on the remote to move discharge boom away from the trailer
Use the remote control to position the discharge over the silo.
Push discharge on
Push floor on
Open the bin closest to the rear – remembering to unload from back to front.
Leave each door open as you move forward.
Check the discharge gauge – it should be around 1400 PSI for 9x9x9 or 1900 – 2000 for 12x12x12.
Check the floor gauge – the PSI should be around 1000 to 1500 for an Auger system – the PSI will depend on which bay you are pulling from or 600 PSI for a Drag Chain from any bay.
Adjust flow control on the floor to achieve 1400 PSI on the discharge gauge – the PSI will vary depending on feed type.
As the bin empties, the pressure will drop on gauges – this is how you will know to open the next bin.
Once all bins are empty, Push the floor off.
Push discharge off
Push lower and in to place the discharge boom back in the saddle
Make sure to close all bottom doors.
For more information, scan the QR code at the front of the trailer or visit [ Ссылка ]
See index of operational videos - [ Ссылка ]
**********
Subscribe and hit the bell to be notified when new videos premiere - [ Ссылка ]
**********
CONNECT WITH US
FACEBOOK - [ Ссылка ]
INSTAGRAM - [ Ссылка ]
LINKEDIN - [ Ссылка ]
TWITTER - [ Ссылка ]
Ещё видео!