Raunak 108 is shaping up beautifully, with every milestone bringing your future home closer to perfection!
* 33rd Slab Shuttering Work In Progress.
* Blockwork - Work Progressed till the 24th Floor.
* Plastic Work - Toilet & Kitchen Internal Plaster Work on 15th Floor.
* Gypsum Work - Punning Done till the 13th Floor, Waterproofing Work, Plumbing Work & Electrical Work In Progress