Construction of the viaduct completed in September 2024.
Work continues at ground level, making good the areas surrounding the piers, and landscaping post haul road removal. Much of the contractors construction equipment has been taken away.
With the temporary jetty/haul road dismantled, an enclosed area of water adjacent to river colne reveals itself...
At deck level, acoustic screens continue to be installed.