How long does a building permit take?
This is a question we get asked ALL the time. 90% of our remodeling projects require a county or city-approved building permit. Because of this, we are unable to start on a project before the building permit is approved!
A natural question we get every single time is: how long is this thing going to take!?
In this video, Brad Bachand explains how long the permitting/planning process takes in the way Home Love Construction does it.
If you have a project you would like a free same-day estimate on, please visit us at this link:
0:00 Intro
0:11 Planning & Permitting
3:14 Third-Party Review Process
4:05 Recap
4:39 Contact HLC for permitting questions!
homelove.construction
Typically, these are the timeline expectations we have for a major remodeling building permit in the municipalities in our area:
Building Permit City Of Dunedin: 6-8 weeks
Building Permit Hillsborough County: 5-7 weeks
Building Permit City of Tampa: 6-12 weeks (depending on variances)
Building Permit Pinellas County: 4-6 weeks
Building Permit Pasco County: 4-6 weeks
Building Permit City Of St. Petersburg: 6-8 weeks
Building Permit City of Clearwater: 5-7 weeks
Building Permit Hernando County: 4-8 weeks (small staff, high variability in timeline)