This video was show how we are launching using Girder methodology. The bridge located at Pahang , Bera Sungai Pahang Kg Guai, the bridge consists 14 span of beam, which is 7 nos per span total 98 nos of T beam. 8 span of bram in the land area, we are using direct launching, balance 6 span of beam which are crossing river we are using Launching Girder System.
Below was machinery and material are using in this launching.
1) Demag Ac 250 ( 250 ton Mobile)
2) Sany SAC 2200 (220 ton Mobile)
3) LinkBelt LS 238 (100 Ton Crawler)
4) Manitowoc Mani 11000 (110 Ton Crawler)
5)Kobelco KOBE 7080 ( 80 ton Crawler)
6) 2 unit of Prime Mover ( Beam Transport)
7)80 Meter of A Frame Girder
8) 300 Meter of Railway track
9) 2 unit of generator set
10) 1 unit of welding set
11) few set of oxygen cutter
We complete the job successfully and zero accident. Thank for all the team who involved in the launching.
Gantry Launching for T-Beam Crossing Sungai Pahang (Bera)
Теги
PahangBeraJKRYB DATO’ Sri Ismail Sabri Bin YaakobMenteri pertahananA-FrameGirder launchingAc 250ScanniaT beamtable topLLMECRLKian BatinTemerlohEast coastDangerousAccidentMan powerTower lightDirect launchingLaunching girderTarik beamtandem lifting with cranestandem lifting calculationtandem lifting safetytandem lifting operationstandem lifting hazardstandem lifting load calculationtandem lifting plantandem lifting plan sample