Drone video from the construction of "Europe" highway - A6 (LOT-3) near Voluyak and Mramor
16.1 km in lenght from 32+447km to 48+903 with gauge A-27 and design speed 110 km/h. It is planned to build 10 large facilities - 1 overpasses, 1 agricultural underpasses, 6 underpasses and 2 bridge.
On July 27, 2022, the contract for construction supervision was signed with DZZD "Europe" with participants "Pathinvest-engineering" AD, "Stroynorm" EOOD and ER JI CONSULTING OOD, with a deadline of 710 days.
On November 19, 2021, the DZZD "Europe-2022" consortium with the participation of Glavbolgarstroy was selected as the contractor with a complex evaluation of 100.00 points based on the evaluation criterion "optimal quality/price ratio"
On October 2024 work began on the last part, which had not been worked on until now - from Voluyak and Mramor to the cloverleaf of the Sofia Northern Expressway and the Sofia Ring Road.
Redistribution is NOT allowed without explicit permit. Any reproductions or distributions of content elsewhere is a violation of the license under which this video is available on the YouTube platform
31.10.2024 - [A6] "Europe" highway - Lot-3
Теги
ЕвропаБългарияМагистралистроежСърбияГерманияroadroads contructionhighwayhighways consrtuctionпътищаТурцияСофияДрагоманСливницаКалотинаHighwaysroads constructionБожурищеВарнаПерникбулдозертрошачкамостовенадлезжелезопътен транспортрекажп надлезГКППтехникапътщрабагstrabagграницаГърцияРъмънияМакедонияпроекткартаSerbiaBulgariaTurkeysila yolusila izinsilaEvropahemusХемус