What is the difference between Validate Scope & Control Scope?
Per the PMBOK Guide:
CONTROL SCOPE: Control Scope is the process of monitoring the status of the project and product scope and managing changes to
the scope baseline.
VALIDATE SCOPE:
Validate Scope is the process of formalizing acceptance of the completed project deliverables. The key benefit of this
process is that it brings objectivity to the acceptance process and increases the probability of final product, service,
or result acceptance by validating each deliverable. This process is performed periodically throughout the project as
needed.