Zameen Phoenix Construction Update – September 2024
Latest Construction Update
- Raft phase 1 pour completed
- Removal of corner struts for retaining wall completed
- Steel fixing for raft phase 2 and lift pit in process
- Steel works for sheer walls started on site
- Pcc and torch membrane for phase 1 completed