Drainage pipes are done, now it’s time for laying fiber fabrics before starting to work with the embankment!😋
I am re - using crushed materials, that has been screened and piled up!
The planned level for the pit is ready, so I adjust the laser - adding the thickness of the new concrete floor, insulation, fine gravel in top layer and a another layer to complete this first layer!
Compaction is also planned into the measuring. Some centimeters are added to the embankment, so the level is correct after compaction!