Work continues around the clock on the Oroville spillway, with concrete taking center stage during the night. Structural concrete is poured for the lower spillway, roller-compacted concrete (RCC) is laid to fill the void in the middle chute, and leveling concrete goes in on the upper spillway. The crew carries on during the day, installing forms for the upper spillway walls, and laying more RCC in the middle chute.