Watch the diagram before the installation
1 - DELTA-UV REACTOR INSTALLATION
Place the unit in a standing position in order to realize the bypass. That will allow easier maintenance and permit the water entrance which must be driven from the bottom and the water exit which must be driven from the top. Avoid putting the unit on the side
In the technical local, install the unit and realize the bypass
Place the pipe joints with a sealing edge. Making sure to place the transparent joint on the top. It will work at the working watering light
Screw in the entrance and the exit without any tools
2 - INSTALLATION OF THE COMBIPOOL
Place the sleeve where all the injection valves are ready installed and the valve which concerned the pH analyst probe. Notice that both injections are opposite on the same valve
Connect the prop with the unit
Unscrew the front face
Place the polyethylene opac on the injection valves and then, after positioning the strainers and putting them in the corresponding drums, position the PVC crystal pipe on the aspirating troops. Be careful! Respect each jump according to every regulation
Fix your front face again
The electrical connection is going to proceed through the filter and control box
Dismount the unit.
Check your two plugs and then you're going to connect your units on the A1 and A2 filtration plots which are located in the filtering control box and then connect the combipool
After installing on the wall, the left technical ballast supply, you can then connect the UV reactor then you start the entire installation. You will notice that your UV lamp is switch on through the white
transplant pipe.
3 - STARTING UP THE COMBIPOOL
Unscrew the front face
Take the battery off and insert it on its connector. Fix it inside the unit and switch it on again your combipool. the elements will be displayed, and the calibration is going to be made
Close the front face
4 - CHANGING THE DELTA-UV LAMP
Unplug or to disconnect the unit first.
Drain the water from the bottom of the unit either by in screwing the nuts or through the drainage cone which exists on some units
When so unit is empty, unscrew the top and take out very straight the unplug UV lamp
Unscrew the sealing nut
Take out the ball quartz and clean it with some white vinegar and a soft rag in order to remove the lamp tracks
Place it again in the unit by putting your finger inside so that it will be perfectly fit in the hole which is located at the bottom of the unit
Screw back again the sealing nut without forgetting to put the joint back
Replace the lamp and reconnected it. This one has an arranged slot which will prevent from positioning it in the wrong side. Do not force it! The four pins have to go in the connector by themselves
Place your top back on though the unit
5 - INSTALLATION OF THE BIO-UV TEMPO DOSING PUMP AND THE BIO-UV PH AUTOMATIC REGULATOR
Install the BIO-UV tempo on the wall
Install the BIO-UV pH automatic regulator carefully respecting the inspiration and injection pipes
6 - INSTALLATION OF THE BIO-UV REACTOR
Install the reactor so that the water inlet is always at the bottom and exit at the top. Avoid installing the reactor in the lying down
Realizing the bypass, connect the union fitting with a specific pliers in order to tighten the fittings