This update was intended for December, but work commenced from December 19 to 21 and concluded around January 3, 2025. A total of 22 girders were installed along Interchange Bridge 3 - Governor's Drive. The working area posed significant challenges due to space limitations and overhead electrical wires. Additionally, the shearline weather caused muddy soil conditions due to rain, and the holiday season contributed to the delay, resulting in the completion on the afternoon of January 3, 2025.
Soon, Governor's Drive will return to its original alignment as the diversion road will be removed to allow for the continuation of the CALAX alignment.
Enjoy watching this development on #CaviteLagunaExpressway. Happy New Year!
Congratulations to the contractor and #MPTSouth / #MPCALA