In this video, we show step-by-step how to install our AL-SC-10 2-Post lift.
Check out all of this lift's features below and if you have any questions leave them in the comments! Have a great day.
Features:
3 Stage Arms/Low 3.75” Profile
Single Point Lock Release in Overhead
Enhanced Strength Single Piece Column
Stability “S” Column Design
Screw-up Universal Pads
Stack-On Truck Adapters
ETL Recognized 220V/20AMP Power Unit
5-Year Warranty including Power Unit
Minimum Ceiling Height Required: 12'
Minimum 4 Inches of Concrete @ 3500PSI
All mounting hardware is included: 5 1/2 x 3/4 Inch Lag Bolts (10)
Timecodes:
Welcome - 00:00
Tools Needed - 00:25
Unpacking - 04:30
Removing from Brackets - 0:12:26
Standing the Post Up - 0:18:21
Positioning the Lift - 0:19:50
Chalkline - 0:28:19
Power Unit Location - 0:29:59
Setup Begins - 0:30:25
Final Positioning - 0:32:15
Anchoring and Drilling - 0:33:14
Shimming (If needed) - 0:38:56
Mounting the Overhead Switch - 0:44:12
Mounting to the Overhead Bar - 0:48:50
Installing Padded Rod - 0:51:30
Final Leveling Check - 0:53:20
Running Hoses and Cables - 0:58:08
Banjo Fitting - 1:00:25
Overhead Bar Bolt Tightening - 1:04:25
Hose Trouble - 1:05:57
Final Cable Running - 1:06:40
Cable Hookup - 1:09:56
Cable Adjustment Part 1- 1:13:00
Power Unit Install - 1:14:31
Arm Install Prep - 1:26:50
Arm Install - 1:29:15
Bracket Install - 1:30:54
Pulley Install - 1:32:40
Testing - 1:33:52
Pulley Adjustment - 1:35:07
Final Tightening - 1:36:45
Lock Greasing - 1:37:56
Slider Greasing - 1:39:37
Cable Adjustment Part 2 - 1:45:35
Review - 1:48:46
Re-torque Jam Nut - 1:50:00
Installing Screw-Up Pads - 1:50:39
Overhead Switch Hookup - 1:53:10
Final Thoughts / Overview - 1:57:43
Tips and Tricks - 2:00:52
Ещё видео!